A risk breakdown structure (RBS) can follow the work breakdown structure (WBS) to identify risk by activity.

Study for the Project Implementation and Management Test. Prepare with flashcards and multiple choice questions, each question comes with hints and detailed explanations. Ace your exam!

Multiple Choice

A risk breakdown structure (RBS) can follow the work breakdown structure (WBS) to identify risk by activity.

Explanation:
Identifying risk by activity is facilitated when the risk breakdown structure follows the work breakdown structure. Aligning the RBS with the WBS means each risk is linked directly to a specific work package or activity, making it clear which parts of the project could be affected and who owns the response. This approach ensures comprehensive coverage, traceability, and easier integration into the risk register, since you can assess and mitigate risks within the exact activities being performed. While RBSs can be organized by risk categories or by phases, matching the WBS provides the most straightforward way to identify and manage risks at the activity level.

Identifying risk by activity is facilitated when the risk breakdown structure follows the work breakdown structure. Aligning the RBS with the WBS means each risk is linked directly to a specific work package or activity, making it clear which parts of the project could be affected and who owns the response. This approach ensures comprehensive coverage, traceability, and easier integration into the risk register, since you can assess and mitigate risks within the exact activities being performed. While RBSs can be organized by risk categories or by phases, matching the WBS provides the most straightforward way to identify and manage risks at the activity level.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy